Lafayette Rail Relocation

Cover photo courtesy of Justin L. Grayson, as was the idea for the post.

When the railroads started coming to towns across the United States, it was a sign of prestige to have a railroad company build a line through the middle of a city street. While the towns thought it was something to be proud of, crossing the tracks was almost impossible. Lafayette was a town of rail crossings…and street running. As I have written about before, Lafayette was the home of several railroad lines. But toward the middle of the 1990’s, this was going to change…with the help of a lot of federal, state and local tax money.

1941 USGS Topo Map of downtown Lafayette, IN.

The actual beginning of discussions about relocating railroad tracks through the city of Lafayette occurred in 1926, when the city first proposed such relocations. Between 1963 and 1973, a series of engineering studies were commissioned by city officials to look at the possibility.

The idea of moving the railroad tracks through Lafayette started moving forward in 1974, when a study was conducted by the Stanford Research Institute (SRI). It was announced by Mayor James Riehle, on 11 July 1975, that a project director was named for the relocation. That director would be Herbert Thomas, vice-president of transportation at Kaiser Engineers, Inc. His local resident manager would be James Ellis.

It was also announced that day that the first two phases of the project would be completed in about ten months from that time. Phase one included the above mentioned SRI study. Phase two would consist primarily of engineering. The final two phases, design and construction, were not put on any schedule as of July 1975.

Mr. Thomas said “relocation plans here are not the biggest he has seen in the country, but said ‘the Lafayette project would be a major one for any city,'” as reported in the Lafayette Journal and Courier of 12 July 1975. He also referred to the “railroad-motor vehicle situation in Lafayette ‘a serious problem,’ noting that on a previous visit he was stopped by a train while hurrying to reach Weir Cook Airport.”

According to the Journal and Courier, “one important aspect of the Kaiser work will be to determine if the negative impact on the Monon Avenue area can be lessened.” Thomas said that “the alignment developed so far can only be reguarded (sic) as preliminary.”

One year later, in July 1976, Kaiser Engineering was set to begin look at the various alternatives to the new railroad location. Project Manager Ken Knevel said that the company would concentrate its work on the riverfront corridor since it received the most support locally. “Everything we’re doing now is just in response to individuals’ comments. The riverfront has been indicated as the preferred corridor.” (Source: Lafayette Journal and Courier, 24 July 1976.) Paul Stitt of the Norfolk & Western and Jack Smith of the Louisville & Nashville both agreed that the riverfront corridor would be best for both their companies’ operations. Conrail’s representative, John Partridge, said “otehr alternative corridors – bypassing the city and using the current N&W and L&N lines – is less satisfactory than the riverfront.”

The Louisville and Nashville, by way of their purchase of the Monon, was running trains through the middle of Fifth Street at the time. However, they did own a stub line that started just north of Main Street (and the Main Street bridge across the Tippecanoe River) traveling northeast to connect to the the street running route, and railroad yards, northeast of Fifth Street. Connecting this stub to the Nickel Plate and Wabash two blocks south along the riverfront would not be that much of a stretch.

Funding was going to be a constant problem, especially from the mid-1970’s to 1980. Washington had become very tight fisted when it came to money. The mayor of Lafayette had gone to Washington DC in March 1977 to ensure that funding would be available for the project through 1980. There were no guarantees.

There were as many as 19 railroad relocation projects in some sort of process in the late 1970’s. Lafayette had gained national attention because it involved consolidating three railroad companies into one line through the city.

Between 1976 and 1978, two neighborhoods were the focus of studies for the relocation plan. Those neighborhoods, the Wabash and the Monon, were going to be directly affected by the moving of the tracks.

The first construction phase finally started in October 1984, when Congress appropriated $7 million. Less than a year later, in September 1985, five homes were torn down to prepare to place Wabash Avenue 23 feet below the relocated train tracks. Things started looking bad again in 1987 when a pending Presidential Veto threatened $20 million in funding over five years for the project…and the insistence from Federal officials that state and local governments pony up 20% of the cost. Something in which INDOT said they weren’t really keen on participating. That veto was overridden by the House and Senate.

The next phase of construction after the override of that veto included a replacement for the Main Street bridge over the Wabash River, new approach ramps to the Harrison Bridge (now Old US 231) and a rail corridor between Ninth Street and Wabash Avenue to replace the Fifth Street street running tracks. A new $11 million North Ninth Street rail underpass was scheduled to being construction in late 1987.

Construction photo of the Lafayette Railroad Relocation, date unknown. Photo courtesy of Justin L. Grayson.

By 1994, the street running along Fifth Street had come to an end. According to the Journal and Courier of 22 July 1994, those were “crossings eliminated today.” Also according to the same newspaper graphic, phase 5 was to be completed in 1998-99 that would relocate the Norfolk Southern’s Wabash double-track corridor to the riverfront route, eliminating 24 crossings from Kossuth Street to Underwood Street.

Lafayette Courier & Journal, 2 August 2003,
announcing the end of the Railroad Relocation
Office in Lafayette.

The project’s offices would finally closed down on 1 August 2003. There were a lot of behind the scenes work that needed to be finished by the office, but the relocation was done. There was also one thing, historically, that was brought up when construction was occurring in 1993. While digging up the foundation of the old Big Four Station in Lafayette, some timbers from the Wabash & Erie Canal were found. The officials with the Railroad Relocation sent those timbers to Columbia, SC, for preservation. They were returned to Lafayette and given to the Tippecanoe County Historical Society for display.

The project would cost a grand total of $186 million in the end. It would not only affect rail transport through the area, but road transport changed as well. The old Main Street bridge in downtown Lafayette was changed to a pedestrian facility. Ultimately, all INDOT facilities in the city itself would be removed…leaving no state or US roads to downtown.

Leave a comment