Marion County Road Names, 1905, Part 1

One of my favorite things to do, if you haven’t guessed, is to look at old maps. One of my interests, especially, is to look at names that are printed on those maps, especially for roads. Seeing how long those road names have been on maps is interesting to me. Since I live in Marion County, and that county has the most available maps online, I spend a lot of time at looking at those. And the road names are very interesting. I want to share some of them today.

The map that I am looking at as I write this comes from 1905. One of the things with this map is that most of the names are on free gravel roads, roads that were, at one point, probably tolls roads. Not completely sure, but it makes sense in the scheme of things.

The first road that I want to mention was called the Fall Creek and Mud Creek Free Gravel Road. The road itself started in Millersville, at the end of the Millersville Free Gravel Road (now Millersville Road). Millersville, on the maps, is located one quarter mile west of the Washington-Lawrence Township line (which runs along what is now Emerson, or the same line, to 62nd Street) on 56th Street. As one can guess, the road name still exists, kind of. Now it is actually in two parts: Fall Creek Road and Mud Creek Road. The road itself ended at the Hamilton-Marion County line (now 96th Street).

Another road name that still exists on this map is the Hague Free Gravel Road. Yes, it is Hague Road today. But there were three extensions to the road that have different names today. First was a mile long, branching from the main road less than one half mile north of the start of the road at the Fall Creek and Mud Creek Road. That extension went west from the main road. Today, that extension is now called 71st Street.

The second extension from the Hague Road branched west, for three-quarters of a mile, one and a half miles north of the first extension. This connected the Hague Road to the town of Castleton. Today, it is called 82nd Street. The third extension, one and a half miles north of the second, branched east for one mile. It is now part of 96th Street.

Back to the second extension, at the end of the Hague Road extension, it connected to the middle of the Andy Smith Free Gravel Road. That road started at Allisonville Road, traveling east along what is now 82nd Street to where what is now Masters Road used to connect to 82nd Street. Here, it traveled north for one half mile, where it turned east for about two miles along what is now 86th Street.

For what is now Pendleton Pike from 30th Street to Oaklandon Road (and its junction with the Bee Line Railroad), had two different names. From 30th Street to Franklin Road, it was the Indianapolis and Lanesville Road. From that point to Oaklandon Road, and north on Oaklandon Road to the Bee Line tracks, it was the Indianapolis and Oakland Road. From here, an extension of the Indianapolis and Oakland Road followed alongside the railroad tracks to the county line. Both of the mentioned roads were also part of a longer former state road, which by 1905 was called the Pendleton Free Pike.

At the Bee Line tracks, heading north, along what is now Oaklandon Road, was the Germantown and Oaklandon Road. This free gravel road stopped one mile south of Germantown, which was located along Fall Creek at the county line (96th Street today). This road ended at 86th Street. From this point, county dirt roads were the way to get to Germantown, which is now submerged in Geist Reservoir.

What is now 46th Street east of the Indianapolis and Oakland Road, for about two miles, was called, at the time, the Asbury Free Gravel Road. This ended at a point half way between Mitthoefer and German Church Roads. From that point, the one half mile to German Church Road was officially an extension to the Asbury Road.

One half mile south of the Asbury Road was the Henry Bell Free Gravel Road. Technically, this road started at the Pendleton Pike, travelled south on Franklin Road to 42nd Street, and ended half way between Mitthoefer and German Church Roads, like the Asbury Road. Unlike the Asbury Road, the extension was on the west end of this path, connecting the Pendleton Pike to Franklin Road along 42nd Street.

Another road name that hasn’t really changed since the 1905 map is Mitthoefer Road. Now, having said that, there is some question as to the spelling of that road’s name, as the family, as I understand it, spelled it “Mithoefer.” I have seen street signs posted by the city of Indianapolis with both two “t”s and two “f”s, as in Mitthoeffer. Today, the city spells it with one “f” (most of the time). This road started at the National Road, running north to the line separating Lawrence and Warren townships (now 38th Street).

One of the most confusing roads, with many names, is now called German Church Road. First, let’s start with its most common name before it was changed by the county to match the interurban stop name along the National Road. From 30th Street south to the National Road, it was called the Franke Free Gravel Road. However, the other name was also commonly used – Holzhausen Road. To make matters worse, the Holzhausen Road had four extensions. One ran east from the end of the main road one mile to the county line along 30th Street. The second ran north from 30th Street to the Peoria & Eastern/New Castle Traction tracks (anyone familiar with the area, that right-of-way, since both the railroad and the interurban are long gone, it is along the north edge of the Hindu Temple of Central Indiana property). The third extension ran west along 30th Street for one quarter mile. The fourth extension ran one quarter mile west from the end of the third extension.

What is now Muessing Road, connecting the Brookville Road to the National Road, was once part of two different free gravel roads. And it gets a bit confusing, to say the least. For starters, the Cumberland Free Gravel Road left that town just like Muessing Road does today, angled to the southwest. From there, just like today, it followed a very curvy path to what is now Prospect Street. Here the Cumberland Road turned east, then south again almost immediately. The Cumberland Road didn’t go far from there. South of Prospect Street, the road makes a sharp turn to the west. Then, before the road turned south again along the half section line, the Cumberland Road abruptly ended. But, the Muessing Extension started at that exact point, running south along the half section line to the Brookville Road.

The last road I am going to cover today, as this will probably be a long series of articles, is the Bade Free Gravel Road. Now, looking at a map of southeastern Warren Township, there is a Bade Road on it. That current road was part of the original Bade Free Gravel Road. For a mile (technically, about a few feet short of one, but who’s counting?), from the Brookville Road to what is now Prospect Street was the beginning of the Bade Road. It retains that name today. However, the Bade Free Gravel Road turned east for three-quarter mile, then turned north for nearly a mile and a half to connect to the National Road. The east turn is now Prospect Street. The last 1.5 miles is now German Church Road.

There are a lot more roads to be listed. I am not sure how many parts this will be…but I don’t want to make them way too long.

Advertisement

Toll Roads In Marion County

Toll Roads. In Indiana, they were a way of life for over half a century. The reason they started was very simple. The counties, after having the state build a road for them, found themselves in a bind when it came to maintaining those roads. So the solution became to sell the roads to private companies, and let them do the work of maintaining the road.

By the 1880’s, the non-existent love affair with the toll road companies was becoming just flat out hatred. Citizens, mainly farmers, were tired of paying to get to the city. This led to just ignoring the toll houses, or finding another way to get to town. This led to the toll companies to lose money. Both sides were arguing for legislation to eliminate toll roads. Residents to make travel cheaper. Businessmen in town to eliminate what they saw as a tax on people to use their businesses. And toll road companies to throwing money at the roads. This led to the counties purchasing these old toll roads back, which I covered in the article “Toll Roads, And State Takeover.”

At one point, Marion County had over 200 miles of toll roads. The county started buying the roads back one at a time. The last road to be purchased, as reported in the Indianapolis Journal of 13 August 1896, was the Pleasant Run Toll Road. The entire four mile length of the road was purchased for $100 a mile. The Pleasant Run Toll Road purchased started at what is now 21st Street and Arlington Avenue, going east for those four miles to end at the Mitthoefer Free Gravel Road. Bet you can’t guess what that road is called today.

The National Road east of Indianapolis started on the way to free road status in September, 1889. The Indianapolis News of 19 September 1889 reported that the “the owners of the Cumberland Gravel Road turned the road between this city and Irvington over to the county this morning and it is now a part of the free gravel road system.” Another benefit of the turnover, at least to Irvington, is that the next day, the Citizen’s Street Railway Company would be granted permission to build a street car line along Washington Street/National Road to Irvington. The plan at the time was to build the street car tracks along the south edge of the road, leaving a 16 foot wide path on the north side of the road for drivers.

In the very same issue of the Indianapolis News, it was reported that “there has been a turnpike war on the Three-notch or Leavenworth road, leading south from Indianapolis to Johnson County.” Residents were claiming that the road was in disrepair, raising money to fight the owner of the turnpike. Many people were running the gates along the road, as there was an agreement to not pay tolls. “At the second gate from the city the pole was cut down by the ‘opposition,’ and there has been trouble all along the line.” A court case in Franklin, the day before, saw the toll road company winning, and the people paying tolls again.

An editorial in the Indianapolis News of 22 June 1892, calls for the remaining toll roads to be taken over by the county. It goes on to talk about the “shun pikes,” local roads built to avoid paying to use the toll roads. The first such “shun pike” in Marion County was English Avenue. It was improved by locals as a way to Irvington without using the Cumberland Toll Road. The next one was Prospect Street, from Fountain Square east.

One toll road that came in from the north became so valueless that the owner of the road tried to give to the county free of charge. Apparently, this wasn’t jumped on by the county commissioners. So the owner went to Noblesville, and had the deed for the toll road transferred, legally, to Marion County. It took twelve months after the deed was registered for the county commissioners to realize that the transfer had even taken place.

The Indianapolis News was the newspaper that was arguing, per an editorial of 22 January 1883, against the county buying the toll roads back. “Why should any county purchase a toll road and make it free? Those who never use it ought not to be taxed to make it free to to (sic) those who benefit by it. While it is a toll road, those who use it pay for it, as they ought.” My, how things can change in less than a decade.

It shouldn’t be lost on people that as the toll roads were being eliminated, the “Good Roads Movement” was starting. While this movement was started by both the post office and riders of bicycles, it would lead directly to what would be known as the Auto Trail era.

Toll roads reached in all directions from the city. In the end, most of the major roads that we use today have been in place for almost two centuries…and had spent time as a toll road. I recommend checking out the following map, which shows the improved roads as of 1895 (Palmer’s Official Road Map of Marion County, Indiana).

Indianapolis Interstates, Planning and Replanning

EDITOR’S NOTE: This entry is for reporting of history, not to choose sides in the planning of the interstate system in downtown Indianapolis. It is merely my intention to report on what happened.

When the first vestiges of the interstate system was being laid down, the plan to connect downtown Indianapolis to the entire system came up immediately. As I covered in the post “Interstate Plans in Indianapolis,” it was already decided, and approved by local, state and federal officials, that the two “major” interstates (65 and 70) would come downtown, while the two “minor” interstates (69 and 74) would connect to the outer loop interstate (465). All that was left were the details.

And as they say, nothing is set in stone until it is set in concrete. Such is the case with the “Inner Loop,” that section of the downtown interstate which is shared by both I-65 and I-70. The rough route of Interstate 70 has basically been decided through the city. Exact details would come later. But Interstate 65 would be a sticking point in the whole plan. The plan approved by local, state and federal officials would be debated for several years.

It came to a head in summer of 1965, when politicians started becoming involved in the routing of I-65…and the building of the inner loop. And the concern that federal funds would run out before the plan was completed.

Indianapolis News, 20 September 1965. The routing of the interstate system through Marion County had already been approved by local, state and federal officials. But that didn’t stop some people from trying to change them.

Up until the point of the summer of 1965, nine years of planning had already gone into the creation of the interstate system in Marion County. Delay after delay, mainly caused by slight variations in the planning, were in the process of being overcome. The whole plan found itself against a hard “drop dead” date, or what was thought to be a hard cap on said date, of 1972. Part of the legislation financing the entire nation’s interstate system stated that the Federal government would continue to pay 90% of the cost until 1972. “The chance that Congress, about five years from now, will extend the 1972 deadline is a gamble state officials cannot and dare not take.” (Indianapolis News, 20 September 1965)

The latest oppositions (in summer of 1965) came from Congressman Andrew Jacobs and City Councilman Max Brydenthal. Their major hang up with the plans was simply that I-65 should turn north on the west side of the White River, and that the inner loop should be completely depressed from multiplex section (where 65 and 70 share the same pavement) west to White River.

The Interstate 65 reroute from West Street west to 38th Street would, according to the proponents, would accomplish five things: 1) the original plan would dead end 40 streets through the west side, and the new plan would require no closing of streets; 2) the new I-65 route could be combined with the already planned SR 37/Harding Street expressway plans for the west side, lowering the cost of building both roads; 3) more interchanges could be worked in, allowing better access, especially to what would become IUPUI and its assorted facilities; 4) historic landmarks would be preserved (mentioned were Taggart Riverside Park, Belmont Park, and Lake Sullivan); and 5) there would be no delay in construction.

From the other side, the proponents of the original plan responded with six points of their own: 1) the original plans were already in the hands of the State Highway Department’s land acquisition office; 2) Construction design plans were already 85% complete; 3) designs for a bridge north of the Naval Armory were nearly completed; 4) the state already spent, or was in process of spending, $2.4 million for right of way; 5) preliminary planning and design fees had already cost the state hundreds of thousands of dollars; and 6) relocation would set the project back three years.

The other bone of contention was the inner loop…and the prospect of making it a below grade facility. As with the actual constructed facility, the depressed section of the interstate project would be from south of Washington Street to Morris/Prospect Street. The desired change would depress the entire center section, and both I-65 and I-70 from West Street to the combined corridor.

Part of the reasoning, used by those that wanted the highway depressed, was quite simply that an elevated expressway would add to the “blighting” of the area where that elevated was built. “In city after city, past experience demonstrated the blighting effect of elevated roadways (most of which are railroad) and we now have evidence that the depressed roadways actually enhance the value of property in their neighborhoods.”

Another bonus point in the depression of the interstate, say the proponents, is that Indianapolis would have a chance to install new sewers, bigger than the ones that were already in place. This included the possibility of the city/state buying snow melting machinery because the new sewers would be able to handle the increase in volume.

The people that had already done the planning pointed out that each section of the planned inner loop had to considered in sections, and not as a whole. Each section of the entire project had been studied and restudied. There was a study done for depressing the north leg of the project (I-65 from West Street to I-70). It had been discarded. The south leg would be partially depressed (at the east end) as would the east leg (at the south end).

One change in the routing of I-65 had already been put in place. On the south side of Indianapolis, the interstate was originally planned to go through Garfield Park. Now, it goes east of that facility.

In the end, the drop dead date of October 1972 came and went without the completion of the expressways downtown. It would be 1976 until they were opened to traffic. The new SR 37 expressway was never built…and now SR 37 doesn’t even connect to downtown Indianapolis. The original routing and elevation, planned in the early 1960’s, was followed as approved.

Madison Avenue Expressway

In the early 1950’s, much had been done to help with traffic issues throughout the city of Indianapolis. With the exception, as pointed out by the Indianapolis News Editorial Staff on 21 June 1954, of the south side. But things were going to be changing soon. The Indiana State Highway Commission decided that there will be another upgrade to US 31 in the state. This time, in the city of Indianapolis on the south side. But many things not only had to come together to do this project, many controversies were unleashed with the project, as well.

First mention of the project, at least in the newspapers, came in August 1953. The Indianapolis News of 6 August 1953 covered the project on page 23. The $3 million project would lower the roadway of Madison Avenue, at the time US 31, some 20 feet to allow for the road to pass under the Pennsylvania Railroad’s Louisville line and the Indianapolis Belt Railway. A large chunk of the money for the project was to be paid out for the acquisition of properties in the 15 block project area. However, most of the coverage in that day’s News was the fact that the State Highway Commission was creating a “District of Dead Ends.” Apparently, the original plan was to start at Morris/Prospect Streets, working south. It was later decided that the work would begin at Terrace Avenue, leaving that street connected to Madison Avenue at the north end of the project.

However, from Terrace to the Indianapolis Belt Railway, no less than six streets were going to be cut in two. Palmer, which actually connected to Madison Avenue at the Pennsylvania Railroad crossing was sure to be removed. Lincoln would be cut off at the Pennsylvania Railroad. Both Minnesota and Iowa would be truncated, as they both crossed Madison in a straight line. Caven did a stutter step type crossing of the state highway. Adler ended at Madison, just north of the Belt. South of the Belt, LeGrande Avenue stutter stepped its way across Madison Avenue, as well.

While the expressway was the major part of the project, that wasn’t the entire scope. From Southern Avenue, one half mile south of Raymond Street, to where Madison Avenue becomes Delaware Street near what was Wilkins Street (now the I-70 overpass), the road would be widened to a six lane facility. Right-of-way would be purchased on opposite sides of the road, with the section from Southern to Pleasant Run Parkway, and from the Pennsylvania Railroad north to Delaware Street being taken from the east side of the street. Between Pleasant Run Parkway and the PRR, the west side would be taken for the project.

A look at a satellite image of the area today shows exactly how much property was taken in each section. The new Madison Avenue is actually west of Old Madison Avenue. (Old Madison Avenue is one of the very few roads in Marion County that includes a hint that it used to be an important facility. And even then, this only occurred when the new street signs started showing up around the year 2000, because prior to that, the street was officially called “Madison Avenue.”) The old road, which sits along the top of the hill that was created with the new road, is in two sections, the the old Belt Railway crossing removed, connecting where Iowa Street was to Raymond Street. All of the property from the old road to the alley between Delaware Street and Madison Avenue was taken for the new canyon expressway.

As an Indianapolis history aside right here, one of the most famous restaurants on Indianapolis’ south side, the Key West Shrimp House, existed in this section of Madison Avenue. It was half way between LeGrande Avenue and Raymond Street (2138 Madison Avenue). By 1955, due to pending construction, it had moved to its more famous location, 2861 Madison Avenue. Almost anyone, of sufficient age, can tell you about the pink building on Madison Avenue that once housed the Key West. Now, they still have a location…at the other end of the road – in Madison, Indiana.

Not only was the road going to be part of the project, in October 1953, it was announced that the ISHC was going to take a “pedestrian census” to see whether a pedestrian bridge would have to be built somewhere in the project area. Plans were to have pedestrian crossings at both Terrace and LeGrande Avenues. However, the project removed the LeGrande Avenue crossing when the construction was completed. The only true pedestrian specific accommodation made in the project area would be a walking bridge crossing at Palmer Street.

Contracts for the first phases of construction of the new Madison Avenue were announced in May 1954. And while the south side of Indianapolis had always been hampered by narrow roads and railroad crossings, causing it to lag behind the rest of the city, it wasn’t long until newspaper editorial staffs began to realize what was about to become a real problem. The Indianapolis News Editorial of 21 June 1954 spelled it out quite succinctly: this is gonna get bad. “Of course, the Madison Avenue expressway is coming – but there will be a crisis for the south side motorists before the expressway is completed.” With the pending closure of Madison Avenue during construction, something that could last up to two years, an already strained city traffic system would be stretched to the limit. And most of that traffic, according to the thoughts of the Indianapolis News, through Fountain Square. “Cars pile up along Shelby, Virginia and Prospect trying to get through the area. This goes on morning, noon and night.” “One improvement has been made. Woodlawn has been straightened and widened between Virginia and Shelby. But the project primarily has provided more parking space and does not help move traffic.”

It would be in December 1954 that the state announced a change in the construction plans. The original idea was that Prospect and Morris Streets would connect to Madison Avenue as they always had, as shown in this snippet from a 1915 map of Indianapolis. Morris crossed straight over Madison Avenue, with Prospect being almost one block north. It is important to note that both these streets are important arteries in Indianapolis traffic. And, they are survey roads, meaning that their location is along a survey line. (That line is Morris Street west of Shelby Street, and Prospect west of it. Shelby Street is a survey correction line, so every street corrects to the north at or near Shelby Street on the south side.) It was announced that the state would create an underpass for Morris Street, with connecting facilities to allow traffic access to Morris and Prospect Streets. As it turned out, east bound Prospect Street became a very long ramp to allow northbound Madison Avenue traffic access to west bound Morris Street. In the same vein, a slightly moved westbound Morris Street became the eastbound Morris to northbound Madison ramp.

This change, along with the grade separation at Raymond Street that had been announced the previous August, were recommended by the United States Bureau of Public Roads, which provided half of the funding for the project. These two changes added over $1 million to the entire project. Construction on the Madison Avenue expressway was “probably” going to start in 1955. But plans for the new changes hadn’t even been worked out as of the announcement, so no one was quite sure of that.

June 1955 saw the start of getting rid of “the old Shrimp House, 18 homes, and an undisclosed number of garages near Raymond and Madison.” The state would be auctioning off the properties on 28 June 1955. Those properties would have have to be moved within 30 days of the auction. The same day that the auction was announced, it was also mentioned that construction was expect to begin that summer. As it turned out, November 1955 came news that the construction would begin in 1956, as contracts had just been awarded for the project.

That didn’t apply to other locations along the project area. It was announced that the new Madison Avenue bridge over Pleasant Run would be opened to traffic on 29 July 1955. The plan was to open four lanes of the six lane span that day. Since Madison Avenue had been closed, at this point, for almost a year, traffic had been slowed to a crawl anyway.

Indianapolis News, 25 September 1956, showing construction of the Madison Avenue expressway at the Indianapolis Belt Railway.

Another sticking point with the local news media, especially the Indianapolis News, was the lack of security when it came to all the old buildings that were being removed in the construction area. This was especially apparent when it came to the fact that there were three schools in or near the construction zone: School 31 on Lincoln Street east of Madison; School 35 at Madison and Raymond; and Manual High School at Pleasant Run and Madison. There were a bunch of buildings that looked like tornado damage, and more than fair share of basements that were just open to the public without any protection whatsoever.

The article to the left, which was published on 22 March 1956, shows the opinion of the Indianapolis News, and the parents of students in the area. Especially at School 35.

Indianapolis News, 25 September 1956, showing the construction area on Madison Avenue, and expressing the Indianapolis News’ concern about the safety of children in the area. An exact location of this photograph has not been determined, but not for lack of trying.

All wasn’t roses on the ISHC end, either. I will cover it in a later post, but irregularities were exposed in 1957 when it came to property acquirement for the Madison Avenue Expressway project. These irregularities were exposed in April 1957, and found itself in court the following October. It involved someone making a ton of money from real estate purchases and sales in 1954 and 1955. Part of the problem was that these types of shenanigans caused the delay of construction, and hence, an extension of the traffic nightmare on the south side of the city. It was, in June 1957, projected that construction would be completed by September 1958.

That construction projection would be close to true, as the 1959 Indiana Official Highway Map cover shows. The new Madison Avenue Expressway was shown in its brand new, completed, status. But even with the completion of the project, the controversy remained. Stanley T. Siegel, Indianapolis traffic engineer, stated, according to the Indianapolis Star, that the project is a “beautiful road that starts nowhere and leads to noplace.” Mr. Seigel took a lot of criticism for that opinion. The problem is, on the surface, he is absolutely right. What he didn’t take into his consideration is the removal of a narrow, overcrowded street (now Old Madison Avenue), and the constrictions placed on it by two busy railroad crossings (which, at the time, they were very busy), and made a better connection with a very busy United States highway running through south central Marion County.

The Expressway would be completely opened to traffic officially on 23 September 1958. It would still be technically closed for another week for curbing and other details, and the interchange at Morris/Prospect Streets would not be ready for several more weeks after that (for railroad elevation just west of the interchange). The project would cost almost $8 million, more than twice the original estimate. It was also announced that the State Highway Department had plans to extend the expressway another 10 miles. This extension would be along State Road 431, also known as Madison Avenue, in the non-bypassed sections of the old road.