West Marion County and I-465

This image has an empty alt attribute; its file name is images.jpg

The first part of the new beltway (almost) around Indianapolis started on the westside of Marion County. As mentioned in other articles, the original plan was to start Interstate 465 at Interstate 65 on the northwest side, with the replacement for State Road 100 (which I-465 officially was) heading south from there to circle around the county from there. Interchanges were planned at I-65, I-74/US 136, 10th Street, US 36 (Rockville Road), US 40 (Washington Street), Weir Cook Municipal Airport (Airport Expressway), Interstate 70, and SR 67 (Kentucky Avenue). According to USGS topo maps, like that included below, show that there was a stub ramp connecting I-465 to 62nd Street, although the ramp connecting to 62nd Street was listed as still proposed six years later.

1962 USGS topographic map showing the original interchange connection Interstate 65 and Interstate 465.

Construction started along the corridor in 1959. The Indianapolis News ran a series of pictures showing the plans set out by the State Highway Department. If you noticed the list of interchanges above, there were no plans for 56th Street or 38th Street to have ways to access 465. Bridges were to be built over 465 at 56th, 46th, 38th, 34th, and 21st Streets. (21st Street was a very special, and contentious, situation. I covered it in the article: “Building I-465 at West 21st Street. [8 May 2020]”)

Indianapolis News, 14 December 1959, showing the Indiana State Highway Department’s plans for the new Interstate 465 (also still called State Road 100 at the time) at the northern terminus of the highway.

The plans for Interstate 65 at that point were to continue to have it replace US 52 (Lafayette Road). The US 52 bypass at Lebanon was made part of the new I-65. The temporary plan was to connect I-65 just southeast of I-465 directly to US 52 until construction could continue. Then I-65 would also be US 52 from that point to northwest of Lebanon. I mention this only because the loop around Indianapolis was, apparently, easier to get approved than trying to run I-65 through town. (And since it would take another 16 years to complete, even to the point that an addition was planned to I-465 and completed before I-65 through Marion County says it all.)

It wouldn’t take long after the original plans for the interstate were laid down that changes were made. The non-planned 38th Street interchange was added to the deal. It was to be a partial cloverleaf interchange connecting to 38th Street at that point. Marion County had decided to build 38th Street from Lafayette Road east to the new White River bridge to be built by the city. At that point in history, 38th Street was a county road with nothing resembling the connections it has today as a major west side thoroughfare.

Indianapolis News, 11 December 1959, showing the future connection to 38th Street from I-465. This ramp would be built much later, when 38th Street was finally connected as a thoroughfare across Marion County.

The next interchange south of the “gonna be built someday” 38th Street was the connection to another interstate highway, Interstate 74. The plans shown in the Indianapolis News differ slightly from what was actually built. US 136 (Crawfordsville Road) is directly connected to the east end of the proposed interstate connection. This would change. It looks like the proposed interchange was moved slightly north, and Crawfordsville Road west of High School Road was turned north to connect to High School Road. This would be where US 136 would ultimately officially end.

Indianapolis News, 10 December 1959, showing the proposed connection between interstates 74 and 465. The original plan, and this was carried out, is that Interstate 74 would “travel over,” ISHD/INDOT term for multiplex, with I-465 from northwest to southeast Marion County.
1953 Topo map showing the intersection of West 10th Street and High School Road.

The next section did change, at least at one interchange, quite a bit. But before I describe that, let’s talk about the placement of I-465 from Vermont Street north to about where 16th Street would be, if it continued to High School/Girls School Road. The new interstate was planned, in that section, to be built directly over High School Road. This is not really a stretch, since High School Road, from Washington Street south to the Airport, was the original State Road 100. And I-465 was, for all intents and purposes, State Road 100 according to ISHD.

I have written a detailed history of SR 100 (SR 100: How did it come to be? [9 March 2019]) and an article about how, at one point, the connection between SR 100 on BOTH sides of Marion County were to have cloverleaf interchanges (“The Cloverleaf Interchanges at US 40 and SR 100” [20 November 2019]). If SR 100 had been completed on the west side, like it was on the north and east sides, I have no doubt that it would have followed High School Road north, probably, ultimately, to 86th Street, which was SR 100 along the northwest side.

The change in interchanges happened at 10th Street. The original plan was for a full cloverleaf interchange at that intersection. This would have pushed the eastbound 10th Street to southbound 465 ramp back closer to Glen Arm Road, where High School Road was rerouted to miss the interchange. What was ultimately built was a jumbled three-quarter cloverleaf with a flyover from westbound 10th to southbound 465.

In the end, High School Road was basically built over by 465 from Vermont to 10th Streets. 10th Street is a survey correction line, so High School actually moves slightly to the east at that point, as shown in the topo map to the left. For more information about survey lines, check out “Survey Lines and County Roads. (29 March 2019)”

Indianapolis News, 9 December 1959, showing the Indiana State Highway Department plans for I-465 from just south of the New York Central railroad tracks to just north of the Baltimore & Ohio Railroad tracks, including what was to originally be full cloverleaf interchanges at 10th Street and Rockville Road.
1953 USGS topo map of the area of Washington Street and High School Road. The area marked “Ben Davis” would be the location of the new cloverleaf interchange between US 40 and I-465.

From the looks of aerial photos in 1959 as shown in the Indianapolis News, the interchange at Washington Street was going to be very destructive. (Keep in mind that as of the writing of this article, MapIndy, my go to source for historic aerial photos of Marion County no longer offers that service. Maps are available, but the aerial photos are gone.) In addition to the shunting of Morris Street (a survey line and historic route of its own accord), most of where the interchange between US 40 and I-465 was basically what had been the town of Ben Davis.

Another thing would have to happen before this interchange would be built. It was determined, and reported, in July 1959 that an improvement of West Washington Street would have to occur before the interstate reached that point. US 40 was to be widened in the area. The work on Washington Street, however, would have to wait until sewer work in the area was completed…probably in 1961. Plans to widen Washington Street from 40 feet to 68 feet wide, with a four foot median and an eight parking lane on each side, were decided upon. Very little of that plan exists today…and if it does, it’s hard to find.

Indianapolis News, 8 December 1959, showing the proposed area of US 40 and Interstate 465.

The last area covered by the Indianapolis News in the series of articles (actually, it was the first since the editor staff decided to post them south to north, even though the interstate was built north to south!) shows the area of I-465 near Weir Cook Municipal Airport. The one change that I can see is what would become Airport Expressway (check out “Indianapolis’ Raymond Street Expressway” [4 February 2020] for the history of what started out as the Bradbury Expressway) was proposed to connect to the airport heading slightly north of due west, just above Southern Avenue. This section of the (now) Sam Jones Expressway is due east-west at the point it connects to Interstate 465. For a history of what is now Indianapolis International Airport, check out “Indianapolis Municipal Airport.” (20 August 2019)

Indianapolis News, 7 December 1959. This newspaper snippet shows the area of proposed I-465 near the (then) Weir Cook Municipal Airport (now Indianapolis International).

That covers the first of the construction of the State Road 100 replacement. I want to share this one last snippet from the Indianapolis News of 19 October 1960. It shows the construction of I-465/I-65/US 52 at 62nd Street…or the original northern end of Interstate 465.

Indianapolis News, 19 October 1960, showing the original northern end of Interstate 465.
Advertisement

US 41 in Gibson County

Princeton, IN-IL, 1:62,500 quad,
1903, USGS

While looking through old USGS topo maps, I found one that caught my interest almost immediately. I have talked over the past year or so about how the current state roads came to be as old county roads from early in Indiana’s history. One that shows this very well is what would become SR 10 in 1919 and US 41 in 1926.

The map to the left shows the county roads between Fort Branch and Hazelton in 1903. Yes, 1903. This is the USGS map, 1903 Edition of the Princeton, Indiana, 1:62500 scale. I have used Microsoft Paint to draw lines of two colors on it. The green lines show where US 41 is today, using the roads as they were in the turn of the 20th century. The blue lines show roads that would be, through history, part of US 41 before it was bypassed. The area in Princeton is harder to nail down, so I included two routes through the town. Both are possible, and since at the time of this map there was no US 41, it didn’t matter which way travelers went.

Historical Topographic Map
Collection, 1942, USGS

As is typical of the USGS, no new maps were truly drawn after 1903 at this scale…at least none that are accessible. What is shown to the right is the 1903 map updated to 1942. It shows several changes in the routing of US 41 between its creation in 1926 and 1942.

First, starting at the top, is the Hazelton Bridge. Construction started in 1921 to replace a ferry near that location. The bridge, as mentioned in the link above to another Indiana Transportation History article, carried SR 10 (and the Dixie Bee Highway, as it was known at the time) over the White River near Hazelton. The bridge was massive. Said to be one of the largest ever built (to that time) by a state highway department in the midwest.

Another section that would be moved before 1942 would be south of Patoka. The road that is now Old US 41 between Princeton and Patoka is actually a replacement. During the 1930’s and 1940’s, the Indiana State Highway Commission made it a point to shorten and straighten state highways. A lot of this put the new location of the state highway next to a section of railroad tracks.

If you have any doubt about this building technique, check out SR 67 southwest of Indianapolis (Kentucky Avenue – moved 1936), SR 67 northeast of Indianapolis (Pendleton Pike, or actually, its replacement), SR 44 from Shelbyville to Rushville (railroad tracks were in place until 1980 or so), and SR 135/252 from Trafalgar to Morgantown (road was built around 1940-1941, tracks were abandoned at very near the same time, although some remnants of those tracks still remain 80 years later).

US 41 would run beside the Chicago & Eastern Illinois tracks between Princeton and Patoka, entering Princeton north of the old route by about two blocks. South of Princeton, the old route was followed toward Fort Branch.

Historical Topographic Map Collection, 1962, USGS

By 1962, several changes were made again to US 41. From Patoka to Hazelton, the route was moved to its current location, replacing the old Hazleton bridge and widening and straightening the road most of the way. There was one section of road that was still two lanes according to the USGS maps of 1962…and that was being rectified.

The old Hazelton Bridge remained in place for years after its replacement by the Indiana State Highway Commission. It would be given to the counties for their maintenance.

At the same time, the current routing of US 41 was also completed. The USGS shows the year of the map as 1961 on the Princeton 7.5 degree quad. (The map to the left is the 1962 update of the 1959 Patoka 7.5 degree quad.)

The major point of this article is to show how the country roads looked in 1910, and before the state started taking over, to give an idea of how one got from point A to point B at that time. These maps, especially those of 1903, really show off the routes that were depended upon early in the history of Indiana. It also shows that, in Indiana, the fastest way between two points is not always a straight line.

County Roads – Getting Named

County road names. Most people don’t give it much thought. A year ago, I wrote an article about the names used around the state for the county roads. Today, I want to look at some of the histories that I have found about the subject.

The subject of naming rural roads was taken up at different times in different parts of the state. Until that point, roads may or may not have had names…but not as some sort of system. Marion County, for instance, had names like Wall Street Pike (West 21st Street from Speedway west) or the name of the resident that paid to have the road maintained. There really was no pattern to any of it.

The Cambridge City Tribune, of 9 August 1900, described the rumblings like this: “In some parts of Indiana a plan is being discussed for having all the county roads named. At the road crossings the names will be placed on posts, something like the old fashioned finger boards. In addition to that each farmer will have his name displayed on a post at the road side at the entrance to his grounds. Something of the kind will be done in all rural districts with the next few years, and it is very much needed. Farmers are beginning to discuss the matter at their meetings.”

St. Joseph County, according to the South Bend Tribune of 2 April 1918, had been working on names for the county roads since the summer of 1917. A plan was accepted and adopted by the St. Joseph County commissioners on 4 March 1918. The current names were placed on the county roads then. In 1934, the South Bend Tribune made sure to point out that rural roads in St. Joseph County were all marked the same way city streets were…with signs hanging high above the road.

The reasons for naming county roads involved things like mail delivery and safety. In the days of the automobile, it made sense to name the roads for travelers to be able to find places. But it started out as an attempt to be able to speed mail delivery. With rural routes all over the state, it was not unheard of that someone’s mail would be delivered to the wrong part of the county. Giving houses numbers, and roads names made mail easier to locate. As for safety, it goes without saying that if the farmer on such and such road had a structure that was on fire, unless the emergency crews where such and such road was, and where the farmer lived, that fire was going to be completely destrucutive.

The most common method of naming county roads in Indiana was called the “Purdue Grid Coordinates.” It is a system where every place in the rural areas of the county are assigned a location based on a central point in the county. This system often involves the north-south middle of the county to be called “Meridian,” and the east-west to be called “Division.” But that is up to the particular county, actually. Some counties do use “00” for the center.

The system was created by researchers for Purdue University’s Joint Highway Research project in the School of Civil Engineering. The plan was to create a system that would allow easier directions for rural areas. For example, the Lafayette Journal and Courier of 9 Jan 1954, used the following example of Doc Smith trying to find Ben Miller’s farm: “take this highway north about five miles, and then instead of turning with the highway at the big pear orchard, continue straight ahead on the County Farm gravel road. It winds a bit, but after about two miles you’ll come to a five-point intersection. Take the road that cuts slightly to the left, follow it to the second crossroad, then turn left. It’s only about a mile from that corner to Wahoo. You’ll have to inquire at the grocery store for Ben’s farm.”

Franklin County, in 1953, was still considering a naming system for the roads of that area. It had been recommended several years earlier, but nothing was ever done.

Hamilton County decided to start looking at their road names in 1958. It started with a report by the Jaycees. That took several years to work on. It was decided that Hamilton County would not use the Purdue grid system, since most people preferred names to numbers. Numbers were assigned from Indianapolis, giving rise to street numbers above 96th to 296th. Each county road, however, that went north and south was given a secondary number to show how far east and west of Indianapolis’ Meridian Street you were. While names were decided upon in the early 1960’s, most addresses weren’t completely determined until the 1990s.

On 10 October 1961 the Rushville Republican printed the following question when it came to county road names: “Is Rush County going to be among the last in the state to get its county roads named and numbered and house numbers for its rural residences? Decatur County is the latest to join the fold. It’s not a costly procedure and it makes it so much easier to locate places in the country. All it takes is a nod, and a bit of cash, from the county commissioners to permit this community to keep up with its neighbors.”

It would be 1962 when all counties in Indiana finally had a system in place, and signs posted. Indiana had passed a law in 1961 requiring all county road intersections to have road name signs posted.

Indianapolis: Indiana Avenue Bridge Over Fall Creek

Early in the history of town of Indianapolis, when the state started building roads to connect the fledgling capitol to the rest of the state, a road was built from the northwest corner of the original Mile Square, traveling northwest. That road would be called both the Lafayette Road and the Crawfordsville Road, since it went to both. After the road crossed Fall Creek one mile north of the center of the town, it took a route closer to White River. That section would later be called Speedway Avenue and Waterway Boulevard. But the bridge over Fall Creek, connecting the two sections, would take nearly two decades for a true resolution. And it required the removing of several streets, including the historic Lafayette/Crawfordsville Road.

1937 MapIndy Aerial photograph of the Indiana Avenue & 10th Street area.

The bridge is question is shown on the above 1937 MapIndy photo. At that time, the intersection at the bridge was a confusing jumble of streets running in different directions. At what became the intersection of 10th Street and Indiana Avenue, there were also connections to Locke Street (heading south past the City (Wishard) Hospital, and Torbett Street running north of 10th heading east. Many people still referred to 10th Street between this intersection and the White River Parkway as Fall Creek Parkway…but that was its old name by the time this photo was taken.

Indiana Avenue had become a major route for people leaving downtown Indianapolis for the northwest suburbs. The northern end of both of Indiana and Speedway Avenues were connected to 16th Street, which ran west from Indiana Avenue to the Emrichsville Bridge over White River. The state had connected separate sections of 16th Street from Indiana Avenue east to Northwestern Avenue as part of State Road 34. Traffic, therefore, was heavy across the bridge.

That was until the summer of 1936.

It was then that the city of Indianapolis limited the bridge traffic to five tons. Trucks and busses found themselves having to go around the closed bridge by using 10th and 16th Streets. In the fall of 1938, the bridge was closed completely to all traffic. Street cars found themselves now being rerouted around the snarl. Indiana and Speedway Avenues north of Fall Creek simply became cul-du-sacs because they had no southern end at all.

The Indianapolis News of 7 May 1943, in an editorial piece, mentions that in 1936, when trucks were banned from the bridge, the Board of Works announced a $110,000 plan to build a new bridge on the site. “In the fall of 1938, the bridge was closed to traffic and a year later the city was promising solemnly to produce a new one almost immediately.”

That was followed in the fall of 1940 by the City Council and the City Engineer coming together to talk about building a new bridge for Indiana Avenue. The City Engineer was “ordered to determine ‘by the next meeting’ the precise status of the matter.” That went nowhere as it was in 1941 that a discussion was held about finding an old bridge from somewhere else to replace the old Indiana Avenue bridge that had, at that point, been completely closed to traffic for three years.

As mentioned above, the editorial was run in the News in May 1943. The bridge was still closed to traffic.

A week later, on 12 May 1943, the Indianapolis News ran another editorial on the same subject. “Mayor Tyndall expresses in one short sentence what many have had in the back of their minds for years about the Indiana avenue bridge over Fall creek. ‘If the army had to cross it, the bridge would be fixed over night,’ he declared. The bridge has stood year after year, closed to all but pedestrian traffic, while tens of thousands of motorists and others have been forced to detour by way of West and Sixteenth streets to get to the baseball grounds and parts of the city northwest of there.”

The News goes on to mention that many times over the past four and a half years, attempts have been made to remedy the situation. Without result. Some of the blame was placed on pending flood control and prevention improvements to Fall Creek. Those improvements still hadn’t happened. The News was advocating for a solution to the bridge issue sooner than later.

And action was taken when Mayor Robert H. Tyndall cut the ribbon on 1 November 1944 to open the newly repaired Indiana Avenue bridge over Fall Creek. Traffic could begin moving across the facility again. Trolley traffic on the Riverside line would start again on 27 November 1944. And everything was great. For almost six years.

The headline in the Indianapolis News of 24 March 1950 read “Indiana Avenue Bridge Out for Baseball Fans.” Simply, it meant that the old bridge over Fall Creek was closed to traffic again. The sticking point, again, came down to whether to spend $35,000 to patch the bridge, or wait until the flood control improvements made it a requirement to replace the bridge. The flood control project, which was estimated to be around $1,000,000, was still in the works as it had been since the early 1940’s.

As it turned out, less than a month later, the city council voted to appropriate $120,000 to fix the old bridge. This was required before bidding could begin on the the contract to fix it. It would seem that it would take longer than expected. It became a political issue when, in October 1951, just prior to the Marion County elections, the political party in charge was blasted for not taking care of a bridge that not only served baseball fans and residents of the northwestern section of the city, but served as an emergency route to Wishard Hospital, which sat just south of the bridge.

The Indianapolis Star said it best in the first paragraph of a story with the headline “City To Spend $120,000 For New Bridge” on 9 April 1952. That first paragraph read “the city is going to sink $120,000 into a new bridge which may be torn down within three years.” While Mayor Clark of Indianapolis was telling the City Engineer to rebuild the bridge, he was also telling the engineer to continue looking into getting Federal money to move Fall Creek 100 feet to the north as part of the flooding control and prevention program.

The flood control issue would finally be resolved in 1959. On 9 August 1960, the old Indiana Avenue bridge was closed once again, this time for good. The bridge was immediately closed and dismantled. It would be replaced by a four lane facility. The flood control project would also require the creek to actually move 100 feet to the north of its then current position, a rerouting of Speedway Avenue, to be renamed Waterway Boulevard, to a new connection with Stadium (Indiana) Avenue two blocks northwest of its historic location, and a removal of Locke Street and Fall Creek Parkway East Drive for the intersection at 10th and Indiana. (The old Torbett Street had long before been cut off from the intersection, becoming a driveway for the old YMCA that stood on the northeast corner of Fall Creek Parkway and 10th Street.)

17 July 1961, Indianapolis News

The new channel for Fall Creek and the new Indiana Avenue bridge was completed in July 1961, as shown in the above photograph from the Indianapolis News of 17 July 1961. The bridge would be opened to traffic as soon as reconstruction of the intersection at the southern foot of the bridge was completed on 1 August 1961. The below MapIndy aerial photograph from 1962 shows the reconfiguration of the intersection, the new location of Speedway Avenue, and the removal of the ends of Locke Street and Fall Creek Parkway East Drive.

1962 MapIndy aerial photo of the area around the Indiana Avenue bridge over Fall Creek.

I-65 and I-465 On The Northwest Side – A Pictorial History

Today, I want to use MapIndy and USGS Topographic maps to show the progression of the interchange between I-65 and I-465 on the northwest side of Marion, just east of Eagle Creek Park. I am going to have four aerial photos in this entry: 1941, 1956, 1962 and 1972. Also, small snippets of several topo maps are used. Strangely, the 1941 and 1956 are almost identical.

1941 MapIndy aerial photo of the area around the I-65/I-465 interchange on the northwest side of Marion County.
1956 MapIndy aerial photo of the area around the I-65/I-465 interchange on the northwest side of Marion County.
1961 USGS Topographic Map of the interchange between I-65, I-465, and future SR 100, now known as I-465.

The 1961 USGS Topo map shows the pending SR 100 connection. Bridges appear in the 1962 aerial, especially Lafayette Road over I-465. It should also be noted that on the USGS maps, the pending I-465 was also marked SR 100. Also, what is now I-65 fed directly into Lafayette Road at this point. This made sense, since I-65 was the replacement, between Indianapolis and Labanon, of US 52…which followed Lafayette Road in this area.

The next photo is from 1962. The missing section in the picture had not changed much, if at all, from the 1956. The Dandy Trail did not cross Eagle Creek at a right angle to the creek. It had been replaced by a bridge on 56th Street. And the reservoir still hasn’t been built. Both interstates, I-65 going straight through the area, and I-465 veering off to the south, catch the eastern edge of the park like area west of Lafayette Road north of 62nd Street. That park like area is listed on the 1953 USGS topographic map as “Eagle Creek Forest.”

1953 USGS Topographic Map of Eagle Creek Forest.

It should be noted that 62nd Street was completely orphaned west of the interstate when it was built. Reed Road, which at the time before the building of the reservoir and the park ended at 62nd Street, was the access to the orphaned section west of the interstate.

The state had already made plans to make the complete I-465 loop, including between 56th Street north to the north leg. However, it never did get federal approval. If it was going to be built, the state would have to build it not as the interstate, but as a state road. Hence it was decided that the road that I-465 was replacing, SR 100, would be the designation for that section.

1962 MapIndy aerial photo of the area around the I-65/I-465 interchange on the northwest side of Marion County.

The topo map of 1967 (1969 edition) shows the completion of Eagle Creek Reservoir and Park. It shows the area that had been the Dandy Trail Bridge over Eagle Creek. I have included two snippets of that map. The first is the I-465/I-65 interchange, with the proposed SR 100 connection. The Second shows the 56th Street causeway over the reservoir.

1969 USGS Topographic Map of the I-65/I-465/Proposed SR 100 interchange.
1969 USGS Topographic Map of the 56th Street Causeway over Eagle Creek Reservoir.

By the time that the 1972 photo was taken, the Eagle Creek Reservoir and Park was in place. Reed Road, which allowed access to the park area with the circular road, was still in place, but as I recall it had been closed to traffic on the 56th Street end. The Dandy Trail bridge had been replaced with the 56th Street Causeway, mainly because the old road was under water at that point.

The major change, relating to the subject at hand, was the completion and connection of the section of I-465 north of I-65 heading off towards the north leg of the bypass route. That section was built not as part of I-465, but as SR 100. It wouldn’t stay SR 100 long, as the Feds allowed it to become I-465…as long as the state continued to pay 50% of the building cost as opposed to the normal 10%. So, yes, that section of I-465 was a state choice…the Feds approved it after construction was started. This would cut even more of 62nd Street, and High School Road, out of the city landscape. The curve, connecting Lafayette Road to 62nd Street heading east, had already cut the corner of 62nd Street and High School Road off from connecting with anything other than Lafayette Road to the west.

1972 MapIndy aerial photo of the area around the I-65/I-465 interchange on the northwest side of Marion County.

It hasn’t change much in that area since 1972. There are some rumblings of changing the interchange to make it more friendly to interstate-to-interstate transfer. But nothing has come of it.

1850: Status of Railroads In Indiana

In an article published in the Indiana State Sentinel of 10 January 1850, the editors of the paper were lamenting the fact that, when it come to eastern knowledge of Indiana, the state basically did not exist. “When any person, other than a resident of the State, speaks or writes of the improvements and resources of the west, them make but one stride from Ohio to Illinois or Missouri, and step entirely over the State of Indiana.” The article goes on to talk about the great strides the state was making in manufacturing and agriculture. But a good deal of the article was shining the light of information on the 18 railroads that were in use, under construction, or under charter, in the state.

“The Madison and Indianapolis railroad comes first, as it was the pioneer.” The railroad spanned a distance of 86 miles from Madison to Indianapolis. Originally, it was built with strap rail, but that had given way to 60 pound heavy “H” rail. 56 of the 86 miles had been, at the time of publication, been replaced with the new rail, with “the remainder is fast being completed.”

2) The Shelbyville Road. Officially known as the Shelbyville Lateral Branch. It ran from Edinburgh, on the M&I, to Shelbyville. Its total length was 16 miles. By the beginning of 1850, it was in “successful operation,” having been built on strap rail 2 1/2″ by 7/8″. Its “successful operation” wouldn’t last long, however. Within the decade, the Shelbyville Lateral Branch would be abandoned.

3) The Rushville Road. This railroad connected Shelbyville to Rushville, a total of 21 miles. At the time, grading had been completed for the railroad, and was quickly installing the same kind of strap rail that was being used at the time on the Shelbyville Lateral Branch. This railroad would last into the Penn Central era, as it was part of the Pennsylvania Railroad’s collection of lines that bypassed Indianapolis to the south and east.

4) The Knightstown Road. This road also started in Shelbyville, heading off to the northeast to connect to Knightstown. The entire road was 25 miles in length. The official name of the route was the Knightstown & Shelbyville. It was well under construction in the beginning of 1850, and was receiving the same strap rail that was used for the two railroads listed above. This railroad had a shorter life than that of the Shelbyville Lateral Branch. By 1855, it was almost gone. And in 1858, an attempt to revitalize the road failed. From there, it just disappeared.

5) The Columbus & Bloomington Road. “Branches from the Madison road at Columbus, and it designed to run to Bloomington, 37 miles west, where it enters the great coal basin of Indiana. A charter for this road is obtained and a sufficient amount subscribed and guarantied (sic) to insure its completion.” I will do more digging, but I can’t see that this road was ever built.

6) Jeffersonville Road. Starting at the Ohio River at Jeffersonville, this railroad ran north 66 miles to Columbus, where it officially ended at the time. It was designed to allow traffic from the Jeffersonville to use the M&I tracks to Indianapolis. It didn’t happen quite that way. The M&I refused to allow Jeffersonville trains on their tracks, starting a disagreement between the two roads until the Jeffersonville just bought the Madison. The railroad, at the time of the subject report, was receiving its iron in the form of 50 pound per yard “H” rail. This road survives today, having been part of the Louisville line of the Pennsylvania Railroad. Today, it is the Louisville & Indiana.

7) Franklin & Martinsville Road. The road that would be 27 miles in length when completed was only located at the time of this article. One half of the route was to be let to contractors in February 1850. The road went through some very hard times in its history. Including seven years of no trains running at all. Eventually, it would be extended to Fairland, and become the Fairland, Franklin & Martinsville Railroad. It would become part of the Big Four, and, as such, part of the New York Central. But it didn’t make it past 1950. In 1942, the section west of Trafalgar was abandoned. 1950 saw it removed from service west of Franklin. The extension to Fairland lasted until 1961.

8) The Lawrenceburgh and Greensburgh Road. (Before you ask, yes that it how they were spelled then. The “H” was dropped at the end of the 19th century, with very few towns putting it back.) “Running from the Ohio River at Lawrenceburgh northerly to Greensburgh, a distance of 42 miles, is at present under construction. The road will ultimately be extended about 30 miles from the latter place to intersect with the Madison and Indianapolis road between Franklin and Edinburgh.” That forecaster route never came into being, as it was eventually built to Indianapolis via Shelbyville. It would become a founding part of the Big Four Railway, and survived through the New York Central, the Penn Central and into the Conrail era.

9) The New Albany Road. Starting in New Albany, the road was designed to connect Salem, Bedford, Bloomington, Gosport and Crawfordsville, a total of 120 miles. In early 1850, it was located and under construction from New Albany to Bedford, some 60 miles. Iron had been delivered to cover 18 miles of that distance. “This road will be in operation to Salem next spring, and to Bedford next fall or winter.” It would go on to become a major part of the Chicago, Indianapolis & Louisville Railway…known to most Hoosiers as the Monon.

10) The Lafayette and Crawfordsville Road. This road was to commence at the end of the New Albany road mentioned above. It would continue carrying New Albany traffic another 28 miles to the Wabash River at Lafayette. It was nearly graded, and will “probably be finished next season.” It, too, like the New Albany road above, would form the backbone of the Monon.

11) The Evansville Road. This road was chartered to connect the 28 miles from Evansville to Princeton. It was speculated by the Sentinel that it would probably be extended another 28 miles to Vincennes, “from the latter place it will either run to Terre Haute, 65 miles, or direct across to Indianapolis, 110 miles, and will in all probability as the country becomes settled, diverge at Vincennes and run to both places.” The premonition came true, as railroads were built to both Terre Haute and Indianapolis. The road from Evansville to Terre Haute would become part of the Chicago & Eastern Illinois. The diverging route to Indianapolis would become part of the Pennsylvania.

12) The Terre Haute & Richmond Railroad. “Commencing at Terre Haute on the State line of Illinois, runs from thence to Indianapolis, 72 miles, and from there 73 miles to Richmond, on the Ohio state line..” The first section, Terre Haute to Indianapolis, was under construction and would be fitted with 60 pound rail when complete. “The second division from Indianapolis to Richmond, will probably be abandoned, and the road diverted from Indianapolis direct to Rushville, and thence across to Cincinnati, via Hamilton, 110 miles, or from Indianapolis to Greensburgh, and thence Lawrenceburgh and Cincinnati, the distance in either case being about the same.”

There was a lot going on in that paragraph. For starters, yes the road from Indianapolis to Richmond was dropped. It would later be built by another company. In the end, it would become part of the Pennsylvania, just like the section from Terre Haute to Indianapolis. The Indianapolis-Rushville-Hamilton-Cincinnati route would also be built, by another company. This road would become part of the Baltimore & Ohio eventually, and formed part of CSX’s only non-former Conrail asset from Indianapolis to the east. The last route mentioned was added to the Lawrenceburgh Road mentioned five paragraphs ago.

13) The Indianapolis and Lafayette Road. Connecting the state capital to the Wabash River, and hence the Canal, at Lafayette, for a total of 69 miles. It was under construction in 1850, and was expected to be completed in 1851. This road would join forces with the Lawrencebugh road above to become a founding member of the Big Four Railway. It would survive into the Penn Central era, but not much past that.

14) Indianapolis and Peru Road. Another route to connect Indianapolis to the Wabash & Erie Canal, this time at Peru 76 miles away. Parts of the route, as of the time of the editorial, were completed using strap rail. “Some portion of it will be in operation next year.” The I&P would became, in its history, part of the Lake Erie & Western, part of the Nickel Plate, and in the end of its mainline life, Norfolk & Western. Parts of this line survive today.

15) Indianapolis and Bellefontaine. Covered yesterday in the entry “The ‘Bee’ Line,” the 83 miles from Indianapolis to the Ohio state line was under construction, and was said to be using heavy rail.

16) The Michigan And Ohio Road. There was a lot going on with the plan of this railroad, which at the time was just being surveyed in sections. Starting at Logansport, the road was to connect to Anderson on the Bellefontaine line. From there, it would connect to New Castle and Knightstown, where it would directly connect to the Knightstown & Shelbyville, thus creating a line from Jeffersonville and Madison to the Wabash & Erie Canal at Logansport. It was also speculated that the road would eventually connect Knightstown to Cincinnati. There are so many future railroads involved in this plan, I will be writing an entire article on this one.

17) Fort Wayne and Muncie Road. Connecting the Wabash & Erie Canal at Fort Wayne to the Bellefontaine road at Muncie 70 miles away. At the time, a charter had been obtained. A line along this route would eventually be built, forming the Nickel Plate line connecting the two cities.

18) Michigan Southern Railroad. The plan was, at the time, that the Michigan Southern would make a detour south at Coldwater, Michigan, forming a “not less than” 100 mile route through Indiana on its way to connecting Detroit to Chicago. The line would be built. It would become part of the New York Central System in Indiana before 1930 when the Big Four was officially absorbed. It still survives today as a heavily travelled route through Northern Indiana.

The article goes on to mention other forms of transportation in Indiana. But that will keep for another day.

Interstate 70 Tidbits

Indiana is the home to four major interstates. Two of those share a route across northern Indiana mainly due to geography. (Let’s face it, Lake Michigan is one of those things that is kind of hard to miss.) The other two connect Indianapolis to St. Louis, Chicago, Louisville, and Columbus, Ohio. Today, I want to focus on little newspaper items that I found concerning the main east-west route labelled as Interstate 70.

The plan in Indiana, as approved by the Federal Bureau of Public Roads, had I-70 being a parallel route to US 40. This would be the case through most of the eastern United States.

According to Indiana state law at the time, the Indiana State Highway Commission was required to publish annually its construction plans for the following two years. While most of the projects would be built, some were placeholders and pipe dreams that still, even to this day, never seemed to appear on any official maps. It should be noted that the plans run from 1 July to 1 July, and are subject to change along the way. And, any project after the ending 1 July (in this case 1965) would be on the following two year plan (in this case, 1965-1967).

In the post “State Highway Department Construction Plans for 1963-1965,” I mentioned I-69 and I-74. One interstate highway left off the original two year plan was I-70. The Jasper Herald of 14 November 1961 mentioned that “there was no Interstate 70 construction in the program.” State Highway Commission Chairman David Cohen mentioned that “the problem is, the route is not approved.” However, engineering work on the route would be conducted during that two year plan. 108 miles of I-70 in all the counties that it would be built would be part of the preliminary engineering projects for the 1963-1965 plan.

One of the projects that came to be with the building of I-70 was a replacement for SR 1. The Highway Commission decided to move SR 1 two miles to the east. At the time, SR 1 entered Cambridge City using Boyd Road and Center Street. It left Cambridge City on Dale Avenue at the west end of the town. The state’s new plan was to move SR 1 due north from Milton, removing the road from Boyd Road and Center Street.

The National Road Traveler (Cambridge City) of 10 June 1965 reported that the ISHC would open bids for paving of the newly constructed Interstate 70 from New Lisbon to its end, at the time, east of Cambridge City. The newspaper reported lamented that an oft used county road would be dead ended at the new interstate highway. Cambridge Road, which leaves Cambridge City as Lincoln Drive, would not have a bridge over the highway. This decision was made by the federal Bureau of Public Roads. What would become Old SR 1 and the New SR 1 would cross I-70. But Cambridge Road, being a mile between each, would not. “A bridge for East Cambridge Road would be the third span in the two-mile stretch between new and old Indiana 1 and would be a waste of funds.”

The Muncie Star Press reported on 28 April 1965 that a contract had been let to Rieth-Riley Construction Company for $2,920,987.69 to build the interstate from south of Mohawk east to 1/2 mile west of SR 209. This included three bridges: SR 13 northwest of Greenfield, SR 9 north of Greenfield, and Brandywine Creek northeast of Greenfield. The traffic disaster that would occur near the Hancock County seat was covered 20 April 2019 in an article “I-70 in Greenfield.”

The 1965-1967 two year plan, according to the Muncie Star Press of 18 October 1962, included a grand total of 21.4 miles of Interstate 70 construction. This only included sections in Henry County, and entering Wayne County. But it involved not only building the road, but also constructing 25 bridges in that section.

The 1971-1973 plan, as reported on 26 June 1971 in the Richmond Palladium-Item, included 5.8 miles of Interstate 70 in Marion County: Belmont Avenue to River Avenue (0.9 mile); south leg of the inner belt (1.5 miles); and from what is now called the North Split to Emerson Avenue (3.4 miles).

Indianapolis News, 15 July 1975.
Indianapolis News, 9 January 1975

State Highway Department Construction Plans for 1963-1965

On 14 November 1961, the Indiana State Highway Department announced its plans for the construction projects for the two year period between 1 July 1963 and 30 June 1965. The two year project between 1961 and 1963 was planned to cost $268.3 million. The 1963-1965 plans would cost slightly less, at $235.2 million. The projected construction would build 408.06 miles of roads across the state.

Of that 408 miles, almost 154 miles of that would be for the interstate highway system. Put on the books to be built in that time was most of Interstate 69 in Indiana. Nearly 103 miles of that road, from Pendleton to the Indiana Toll Road, were to be placed under contract and built starting in July 1963. It would focus on two sections: Pendleton to southwest of Fort Wayne; and US 6 to the Toll Road.

Another interstate project, accounting for 17.7 miles of road, included Interstate 74 from Lizton to Crawfordsville. This was a continuation of the interstate from its then end at Lizton, which would be opened in the fall of 1961 from I-465’s west leg to Lizton.

Another interstate project included in the plan was that of Interstate 65 in Lake County from the county line to the toll road. This project included 22.7 miles of new interstate highway.

David Cohen, State Highway Commission chairman, stated that the construction of connections with I-65 and I-69 would help the “financially-ailing toll road.” In addition to the new interstate connections, the Toll Road Commission would be helped by their own lobbying. The Highway Commission had been put under pressure to slow construction on the Tri-State Highway, a toll free alternative to the turnpike. No projects involving the Tri-State were listed in the 1963-1965 plans.

Marion County would have its share of projects in the Construction Program. Interstate 465 would be the biggest recipient. Construction of the highway from Raymond Street to 56th Street was the largest part of the plan. Also, if the design and location of the east and north legs (from 56th Street to I-65 near Whitestown) was approved by federal officials, preliminary engineering and right of way acquisition would be conducted as part of this program.

At this point, the rest of I-465 (west and south legs) was opened, under construction, or in the 1961-1963 program. The plans for the east leg included 21 road and railroad grade separations and a bridge over Pendleton Pike (US 36/SR 67).

Three preliminary engineering projects involving the Marion County interstates were also included in the 1963-1965 program: I-65 north and west from 16th Street west of Methodist Hospital; I-69 from Pendleton to the north leg of I-465; and I-70 from I-465 west leg to West Street. Cohen mentioned no time table for the beginning of construction of the interstates in Indianapolis, but said that a section of I-65 from 38th Street north and west could be part of the 1965-1967 program.

There was a lot of other projects on the 1963-1965 program. SR 67 from Martinsville to Mooresville was to be expanded into a divided highway, and some of the kinks were to be eliminated. The new SR 37 from the south leg of I-465 to 38th Street, and divided highway treatment for 38th Street from Northwestern Avenue/Michigan Road to Capitol Avenue were also included. The SR 37 project was never completed.

A new SR 431 was also planned, starting at the north leg of SR 100 (86th Street) to US 31 at the north end of Carmel. This project would tie the new SR 431 to US 31 near the junction with the then current SR 431. At the time, SR 431 was Range Line Road/Westfield Blvd. The new SR 431 would become known as Keystone Avenue…now Keystone Parkway through Carmel.

Indianapolis News, 14 November 1961. This map shows the extent of the 1963-1965 State Highway Department Construction Program. Solid black lines show the 1963-1965 plans. Dotted lines show the 1961-1963 plan.

Building I-465 at West 21st Street

When the interstate system worked its way to Indiana, the plan for a bypass around Indianapolis was on the books as part of the project. Even before the route numbers were nailed down, the destinations and relative locations were in place. What would become I-465 would take almost a decade to build – more if you count the section from I-65 to I-865 on the northwest side of Marion County. (For more information about that statement, see “The Beginning of I-465,” published on 16 May 2019.) But I-465 was contentious…and not entirely for the reasons one would think.

Indianapolis Star, 11 August 1961.

The first real bone of contention (other than the coming destruction of entire sections of Marion County) was the area where I-465 and 21st Street meet on the west side. The section of the current interstate from Crawfordsville Road south to almost 10th Street runs very close to Big Eagle Creek. The town of Speedway at the time suffered from flooding on a regular basis. The state planned for 21st Street to cross over the interstate. Local residents, and county government, wanted the opposite…the interstate to cross over 21st Street. Part of the argument was that the state had already planned to elevate sections of the road on both sides of 21st Street. Why not keep the elevation for the 21st Street section.

Part of the argument was flooding…or the potential for such. People in the town of Speedway were under the impression that running 21st Street under the interstate would form a valve to keep flooding to a minimum. As the Indianapolis Star pointed out in an editorial piece on 24 August 1961, “nothing could be further from the truth.” The interstate was graded far above the maximum flood level at Eagle Creek. The building of an underpass for 21st Street, it is pointed out, would require a complete new system of levees to be built to control the flooding of 21st Street. The problem for Speedway and flooding was not an interstate overpass, but major work needed on Eagle Creek.

It was pointed out in another article that the plans for I-465 included, in the embankment for the bridges, four channels for water to flow through the area not actually in Eagle Creek. The Indianapolis Star of 9 July 1961 reported that Joseph I. Perrey, chief engineer for the Indiana Flood Control and Water Resources Commission, stated that no matter what was built at I-465 and 21st Street, the problem with Speedway flooding was more controlled by the 21st Street bridge over Eagle Creek. “The construction of 21st Street either under or over Interstate 465 will have no affect in stopping flooding.” Mr. Perrey continued “but a new county bridge could alleviate the situation somewhat.”

Progress was made towards changing the state’s mind about the 21st Street overpass. Summer of 1961 saw a flurry of activity. The state agreed to change the project, if the county put up a $50,000 bond to cover any cost overruns due to the change. The deadline for the county agreeing to that provision, and thus the contract to change the plans, was 21 August 1961. County Commissioners agreed to sign the deal that day, if they could include a provision to delay the posting of the bond. By law, the county said, it would take five days to make the money available.

But the State Highway Commission was also in a bind at this point. Construction had reached a point where concrete was ready to pour. Any delay in that poring could have resulted in the contractor suing the state. In addition to the changing of 21st Street from an overpass to an underpass, the county was asking that 21st Street be built four lanes wide, instead of two, to “avoid a greater expenditure if 21st must be widened later.” (Source: Indianapolis News, 21 August 1961)

The whole thing was made worse when the county questioned the state about the current status of the contract. (Source: Indianapolis Star, 8 September 1961) “The State Highway Commission yesterday refused the ‘bait’ offered by the Marion County Board of Commissioners to cancel the contract obligating the county commissioners to pay for the time the state suspended operations on Interstate 465.” The state was expected to send the county a bill for the six day shutdown of construction on the interstate due to the county trying to raise the bond money. The county, for its part, wanted the contract to be declared cancelled…which the state wasn’t having.

Add to this, the county stating that they weren’t paying anything until a full accounting was relayed to them. They expected it to be, roughly, $1,000 a day, not the $25,000 the State Highway Commission expected.

Meanwhile, the whole decision to build a 21st Street bridge over I-465 was being investigated by the Federal Bureau of Public Roads. That investigation started when three local residents accused the Highway Commissioner of conflict of interest, and hinted that his three sons would benefit from the building of an overpass. Indications were that libel suits would start flying from the Commissioner’s sons once cleared by the Federal investigation.

“The controversy over the intersection of I-465 and 21st Street was started by Jules T. Gradison who owns the land around the intersection. He demanded that 21st Street pass under I-465 and the state agreed to the change when the county commissioners offered to pay the extra cost, estimated at from $150,000 to $200,000.” Mr. Gradison also pointed out that he would have given any extra acreage needed to change the plan free of charge.

21st Street crosses over I-465 to this day. The overpass is also, to this day, only two lanes wide. With the many reconstructions of I-465 through that area, the 21st Street overpass has allowed for the widening of 465 needed over the years.

Bridge at New Harmony

Along the Wabash River is the town of New Harmony. The town dates from 1814, founded by the Harmony Society under the leadership of George Rapp. The Harmony Society was a group of German Lutherans that had separated from the official church and immigrated to the United States. That group, by 1824, moved back to Pennsylvania. The town then was purchased by Welsh industrialist Robert Owen for the purpose of creating a utopian community. That plan failed, but the community did contribute to American society.

Fast forward around 100 years. On 1 May 1928, the United States Congress chartered a private company, the Big Wabash Bridge Company of Carmi, Illinois, to build and maintain a bridge crossing the Wabash River between Carmi and New Harmony. Built by the Nashville Bridge Company of Nashville, Tennessee, the bridge opened to much fanfare on 30 December 1930. The bridge, as originally designed, is just shy of 2,600 feet long, with a 20 foot wide roadway on 47 spans.

Shortly after opening, the Indiana State Highway Commission made the New Harmony Toll Bridge a part of SR 66. Within a decade of that opening, ownership concerns began occurring. A bill passed through the Indiana General Assembly in 1939 created what was to be called the Indiana Toll Bridge Commission (ITBC). The ITBC was immediately asked by the Harmony Way Bridge Company, the then current owners of the bridge, to purchase the structure. Opposition to the bill creating the ITBC was questioning the end purpose of the commission, as State Senator Roy Dentiston, Rochester, stated, the bill was introduced in “an attempt to pull the irons out of the fire for somebody.” (Source: Indianapolis Star, 12 August 1939)

The bill became law without the signature of then Governor M. Clifford Townsend. Once the ITBC was created, questions also crept up about the fact that the commission was meeting behind closed doors. Meetings were held with various people “in the event the commission should buy the New Harmony bridge.” “‘No commitments have been made to anybody,’ George C. Simler of Corydon, commission president, said.”

The plan to buy the bridge went through in 1940. The ITBC agreed to buy the bridge, built for $640,000, for $945,000, with a surplus fund of $105,000 for emergencies. Governor Townsend had already blocked an effort, in 1939, to purchase the bridge for $1.3 million. The ITBC was in the process of not only buying the bridge at New Harmony, but building a toll bridge at Mauckport. Bonds for the purchase were sold, dated 1 October 1940 with a maturation date of 1 October 1960. But, the ITBC pointed out, that tolls collected from the bridge would not only retire the bonds in eight to ten years, but that the bridge would be made free to use around the same time. Operation costs were estimated to be $15,000 to $16,000 a year including painting, maintenance, and insurance.

The fallout from both the creation of the ITBC and the pending purchase of the Harmony Way Bridge was massive. Lawsuits were filed in the matter. The Indiana General Assembly heard a bill repealing the creation of the commission. The biggest complaint was the purchase price of the bridge. A. S. Thomas, representing the Indiana Farm Bureau, “said engineers have estimated that the bridge could now be built for approximately $475,000.” (Source: Indianapolis Star, 29 January 1941) “We consider the purchase price not based on good judgment. I am not trying to keep anyone in southern or western Indiana from having a bridge, but we are interested in the people who use that bridge,” Thomas added. Attorney for the ITBC, Lew O’Bannon (grandfather of future Governor Frank O’Bannon), explained that “at the present rate of income from the bridge it would be paid for in approximately 10 years and then converted into a free bridge.”

In the end, the state did not purchase the New Harmony bridge. Later in 1941, the United States Congress created a joint Illinois-Indiana agency called the White County Bridge Commission (WCBC) to purchase the structure for $895,000. This would be the organization that still owns the bridge to this day.

Tolling facilities had been on the eastern end of the bridge until replaced, in 1951, with the toll house that still exists on the Illinois side of the river.

In 1957, the Army Corps of Engineers warned that the structure was in danger of being destroyed or cut off by the Wabash River. (Source: Terre Haute Tribune, 31 May 1957) Testimony occurred before the House Public Works Appropriation Subcommittee asking for $405,000 for the shoring up of the west bank of the Wabash. The river had been developing a series of new bends. These threatened the stability of the bridge. The new channel being created by nature could have cut the bridge off from Illinois completely. Louis C. Rabaut, Democrat Representitive from Michigan, pointed out that during the Wabash Flood of 1943, the New Harmony bridge was the only crossing of the Wabash that remained open.

In 1961, the operations of the White County Bridge Commission came under Congressional scrutiny. Senator Robert S. Kerr, Democrat of Oklahoma, Chairman of the Senate Public Works Committee, announced that “his committee now wants to learn all about the manner in which the bridge at New Harmony, Ind., is operated. He said full investigation and hearings will be held.” (Source: Indianapolis Star, 22 September 1961) The whole ordeal was started by Representative Winfield K. Denton of Indiana, who had been trying to end the White County Commission for the previous six years. The effort was to free the bridge of tolls. Denton had put in a “secret amendment” into a bridge auditing bill to allow the Secretary of Commerce to name a new commission for the bridge, after wiping out the then current one. Denton stated that the facility had collected $4 million in tolls since the creation of the commission, but was still a toll bridge. The General Accounting Office had issued a scathing report in 1955 about the commission, prompting the entire scenario. After these hearings, the commission was left in place.

Funding became a serious issue, coming to a head in 2001, when the Illinois Department of Commerce and Community Affairs granted the WCBC a total of $120,000 for upgrades to the facility. The plan was to close the bridge at the end of 2001. At this point, the facility was in such poor condition that neither state wanted to take over operations and maintenance. It was, according to the Indianapolis Star of 12 December 2001, estimated that $2.2 million to $3.6 million would be required to bring the bridge up to Federal standards. It was also estimated that it would cost $25 million to replace.

According to the same article, the bridge had dropped its tolling earlier in 2001. This didn’t last very long. Daily average crossings, in 1999, numbered 2,660 vehicles. In October 2001 it was announced that the bridge would be closed by the end of that year. That ended up not happening. Officials of New Harmony were pleased with that news, as “closing the bridge would double the driving distance between the two towns (Carmi and New Harmony) from seven to 14 miles. That could be dangerous for emergency vehicles or people trying to reach a hospital.”

September 2007 did see the closing of the facility…but not permanently. Damage to one of the concrete piers warranted the closing for emergency repairs. At this time, the WCBC was operating on an annual budget of $460,000, not enough to keep the bridge in good condition. Again, the commission asked the departments of transportation of both Illinois and Indiana to take over the bridge. And again, this was shot down due to the cost of bringing the bridge up to federal standards. The bridge would reopen in April 2008.

In September 2011, it was made public that the bridge was in need of $8.4 million in repairs to bring it out of “structurally deficient” status. (Source: Seymour Tribune, 30 September 2011) This status was also applied at the time to the Sherman Minton Bridge carrying Interstate 64 over the Ohio River near Louisville. The difference between to two structures was that the Sherman Minton Bridge was a state owned facility. It also carried much more traffic. The end of the bridge’s useful life came to an end in May 2012 when it was announced that it would be closed at noon on 29 May 2012. This was announced by the WCBC on 21 May 2012. Unfortunately, that 29 May date was pushed up to immediately, as in 21 May 2012.

Today, the bridge still stands. It has been cut off from both ends, abandoned in place. Indiana SR 66 and Illinois SR 14 are still maintained up to a point near the approaches to the old structure. It is listed on the National Register of Historic Places, having received that honor in 2007.